Changes in the scope of work on a major project are a common occurrence in the construction industry. Contractors are accustomed to directed changes, that is, those changes ordered by the Owner or the Owner's agent under the change order clause of a contract. However, the nature or extent of construction work is often changed without the initiation of a change order. The question of compensation or time extension for this type of change is not as clearly addressed by the contract as are the responsibilities mandated by directed changes. This situation is commonly referred to as constructive change. A constructive change arises when the Owner acts in a manner that has the same effect as if a formal change order were written. If an unwritten change occurs, which would have been enforceable as a directed change under the contract ...