Most would agree that the earlier a construction dispute, or potential dispute, is
addressed, the better the chances of a fair and prompt solution. Undisputed
facts may be available at the time of occurrence, facts that often become
muddied with time and emotions.
But acting promptly is not enough in
itself. All potential disputes must be accurately and fully documented as they
occur - not reconstructed with hindsight based solely on project cost overruns.
By observing the following simple guidelines, it is possible to keep most
construction difficulties from escalating into expensive, drawn-out
claims.
1. Planning: An effective project manager should ideally spend
more time anticipating potential trouble areas to be avoided, rather than
rectifying problems that have already occurred.
2. Recognition: Recognizing a
potential dispute situation as it unfolds is the key to avoiding claims or
minimizing their impact. Knowledge of the different types of claims enables a
contractor or owner to take action to avoid a claim, or even worse,
litigation.
3. Communication: Develop open communications between empowered
people on both sides. Let the decision makers talk to each other; otherwise,
precious time is wasted, and an accumulation of seemingly insignificant issues
may begin to restrict progress. Owners should be aware that their
representatives may be reluctant to acknowledge a problem in an attempt to
"protect" the owner from any additional costs. Similarly, contractors should be
aware that their managers may seek to escape the consequences of their own
faults by blaming others, particularly the owner. Both situations lead to
confrontation, especially when an owner receives an unexpected claim near the
end of the project.
4. Definition: Do not ignore a problem, or its
potential consequences, in the hope of a more favorable settlement after the
work is complete. Once a problem is established, it should be defined and the
parties should reach a consensus, if possible, in terms of impact, extent, cost,
and plausible solutions. By establishing these parameters and rationally
assigning responsibility, it is more likely that the parties will reach a
mutually acceptable solution.
5. Notification: When a
problem arises, the contractor must promptly inform the owner or the owner's
representative in accordance with the requirements of the contract, and the
owner must promptly respond. Failure to do so, by either party, could result in
a claim and/or litigation. Each party should provide factual evidence to
substantiate its position.
An untimely or poorly prepared submission places
both parties in difficult positions, severely limiting options and resolution
mechanisms. After-the-fact submissions for schedule impact and/or additional
compensation are generally, and understandably, viewed with
suspicion.
6. Documentation: Accurate, up-to-date project records are critical
throughout a project, especially during the negotiation and litigation
processes. Since contemporaneous project documents usually provide the most
reliable account of a project's history, it is imperative that a
well-documented, logical cause-and-effect relationship exist between any
unanticipated events and their consequences. Without this information it may not
be possible to demonstrate the full effects of the events that
occurred.
7. Contract Documents:
The contract documents should be fair
to both parties and as specific as possible, as warranted by the nature of the
project. One-sided contracts promote disputes that often end in litigation. With
the increasing complexity of facilities, it has become correspondingly important
to prepare accurate contract drawings and specifications that the contractor can
readily interpret at the bid stage of a project.
8. Cost and Schedule Impact:
In addition to the obvious direct cost associated with any change, the
contractor should establish detailed schedule implications (direct and indirect)
of the delay/disruption to the project completion date and intermediate
milestones. Contractors must be confident they have the resources to undertake
additional work and consider any potentially damaging effects on the regular
scope of work. This exercise will enable the owner to make a well-informed
decision and possibly provide an incentive to work towards a more timely
solution once the schedule's critical activities are analyzed.
The fact that the
contractor loses money on an element of work is not, of itself, entitlement for
a claim, nor should the contractor build in excessive profits on extra work
dictated by the owner or circumstance. Such action may undermine the
contractor/owner relationship and destroy credibility. The owner must recognize
the contractor's right to compensation and fair profit on any additional work
the contractor is required to perform.
9. Administration: Parties
should administer change orders as they would new contracts, promptly and in
accordance with contract requirements. Change orders should clearly define the
scope of the additional work and clearly delineate between direct and indirect
costs when applicable.
10. Solution: One party is often in the best position
to recognize the most cost-effective method to deal with a particular problem.
This knowledge should be used to establish acceptable alternatives that will
reduce the other party's exposure. However, neither party should assume total
responsibility under the proposed alternative. Thus, mutual contribution or
consensus remains an integral part of the process. Deviations from the original
contract will create new areas of exposure and responsibility. Definition and
reasonable allocation of this additional risk and responsibility can reduce the
typical finger-pointing that can begin as soon as problems
arise.
The Next Step
Inevitably, some disputes will remain unresolved. This does
not mean that the parties should "revise" their positions, pull in unrelated
incidents to discredit other parties, or inflate claims in anticipation of a
compromised settlement, as all of these actions jeopardize the fair and
efficient resolution of a legitimate claim. If efforts to avoid a claim
situation at the project level prove unsuccessful, effective documentation will
remain useful as favorable testimony and form a solid basis for future dispute
resolution.
Disclaimer: This article is intended to be a source of general information on a specific construction-related topic. Its content should not be considered legal advice. If you are seeking legal advice, please consult with professional legal counsel. For assistance in assessing a specific construction-related issue, please contact Interface Consulting directly.
Rating: 5.00 / 5.00
-
1 ratings
For additional information on this Construction Management article, please contact:
Interface Consulting
Related Documents:
Content Tags: construction management • interface
Other Recent Articles:
Return to the Interface Consulting Articles Search Page
© 2009 Interface Consulting International, Inc.